Resolution Copper remains resolute, reaches milestone

Photo via Resolution Copper Facebook

(Disclosure: Rose Law Group represents Resolution Copper.)

By Copper Area

It was a big job, but somebody had to do it.

To nobody’s surprise Resolution Copper got it done. Shaft 10 was a challenge, but their incredible team of local miners from Superior rose to the occasion, pouring their heart and soul into the complex project. It was a true showcase of teamwork at its absolute finest.

The team at Resolution Copper reached a major milestone. The ductwork in Shaft #10 is complete!

Highlights of this project, achieved by this stalwart crew are over 2,200 feet of ducting removed, 29 shifts dedicated to duct removal, an average of 73 feet removed per shift and a jaw-dropping maximum of 150 feet removed in a single shift.

READ ON: